What is the basic content of electrical commissioning work? |
* Answer
(1) Adjustment tests for complete sets of electrical control equipment and systems, including primary and secondary equipment and various control equipment and devices, during and after installation.
(2) Power-on checks the interaction and interrelationship of all electrical equipment and control devices. 6) Write debugging schemes for complex equipment and devices, test plans for important equipment, and system startup plans. (7) Participate in the technical guidance of some experiments. (8) Responsible for the electrical commissioning work and technical guidance of the clearance operation during the startup of the complete equipment. |